Interim North Lake Forcemain


What’s happening on East Lake Sammamish Parkway SE?

IMG_0621

 Interim North Lake Forcemain

Estimated Project Budget: $5,435,000  

Estimated Project Construction Timeframe: May 2023 – Sept. 2024

Started construction on May 1, 2023. Traffic revisions in place throughout construction period. Paving is anticipated for late August/early September.

All 5,700 feet of new sewer line between East Lake Sammamish Parkway SE and East Lake Sammamish Place SE. has been installed and in service since October 2023.