- Interim Central Lake Forcemain
What’s happening on East Lake Sammamish Parkway
Interim Central Lake ForcemainCompleted
Estimated Project Budget: $1,590,000
November 2022 – May 2023
Traffic revisions have been lifted and all lanes are open are on East Lake Sammamish Parkway between 3350 East Lake Sammamish Parkway SE and SE 37th Street. Sammamish Plateau Water installed 1,000 feet of sewer line between Nov. 7, 2022, and February 1, 2023. The new sewer line is in service and final paving is scheduled for April 2023 when the weather conditions will be more favorable for paving operations.